Exeter Main Street - Weekly Update - December 13, 2024

This week the contractor completed any remaining paving planned for 2024, temporary line markings were painted, and the site prepared for winter shut down. All lanes on Main Street have been re-opened and there is full access to all businesses. This is the final update of 2024 until the spring of next year when the contractor returns to complete the final surface works.

Your patience and understanding throughout this project has been greatly appreciated. Thank you!